SYSE.Application:4.3 - 3. Restore parity and choose the next probe
The comparison uses the same three operating conditions, commissioning date, field interfaces, configuration
evidence, assurance burden, data access, support horizon, internal capability consequence, expected change
latency, and exit condition. Judge the provider demonstration and the unfinished internal prototype against the same acceptance basis:
the accepted GH-2 configuration and representative operating conditions.
The custom provider’s sixteen-week estimate exceeds the need-date limit. Timely completion of the internal-only arrangement remains unsupported. The ready-controller and hybrid arrangements still need evidence for the protected conditions. The hybrid’s expected advantage for later greenhouse-specific changes depends on the supported interface, its timing, configuration export and fallback.
The ready-controller arrangement costs EUR 84,000 and eighteen internal engineering days; the hybrid costs EUR 96,000 and thirty-two internal engineering days. Both current estimates fit the need date; the remaining realization conditions must still be established before relying on those estimates. The operating plan expects at least three greenhouse-specific changes in the next three years, so the deciding management team will prefer the hybrid when its added price stays within EUR 15,000 and its added internal burden stays within fifteen engineering days, but only after the protected interface and fallback claims are supported.
The same team is authorized to spend up to EUR 7,000, forty engineering hours, two hardware-in-the-loop laboratory
days, and five elapsed working days on this decision. The safety specialist separately authorizes the failed-
sensor injection in the laboratory. ChoiceResult-GH2-1 is probe again: a EUR 5,500 replay uses thirty-two
controls-engineering hours, eight integrator hours, two laboratory days, and the available five-day reserve.
The decision rule distinguishes four outcomes. Unsafe fallback or unusable configuration export rejects both survivors. Safe fallback and export combined with failed supervisory timing or unsupported API retains only the ready-controller arrangement. If fallback, export, API support, and timing all pass, both survive and the stated price-and-burden rule retains the hybrid. An interrupted or inconclusive replay that exhausts its authorized limits leaves the protected claims unresolved and returns the commissioning-plan question; it does not establish controller failure or permit commitment through the gap. Before the replay, neither survivor has enough evidence for a choice under the declared rule; rejecting both would discard an arrangement that the bounded replay can retain.
The example assumes continuing vendor support for the tested API and interface version. The replay establishes the other parts of the third outcome: the local controller enters the supported fallback without an
unsafe actuator command, the supervisory command round trip remains below the application-profile limit, and the
configuration export reidentifies the tested controller and software values. The safety specialist limits the
first observation to the tested failure and configuration. The deciding Agent applies C.11 again and records
ChoiceResult-GH2-2: choose now for retaining the hybrid as the arrangement whose next realization
contribution is to be developed. The replay qualifies fallback, configuration export and interface timing for the tested configuration. Continued support for its API version is a separate premise. The replay does
not establish that internal integration and commissioning can be completed by the need date; commitment
to that delivery still depends on the contribution below. A different safety limit or withdrawn
vendor-update support would reopen the obtaining choice.