OPS.10.2:4.5 - Choose early work, deferred starts and protection

Compare start policies inside the feasible windows. Starting earlier can reveal problems and retain recovery time. Deferring can avoid aging, premature expenditure or work invalidated by a later input. Retain the recipient’s original waiting boundary in either comparison.

When protection is needed, name the event and disturbance to be absorbed. Choose an internal target earlier than the commitment, or reserve time before a consequential join. Determine its amount from the delay scenario, supported bound or risk model that matters to the decision. A final margin is available time; calling it a buffer adds a policy for preserving and using it.

When several operations protect the same delivery, compare keeping their individual protection with placing protection before the common delivery or a feeding join. Revise the operation estimates and protection together, preserving the required work, intermediate obligations and execution conditions. Size the shared protection for the joint delays it must absorb: delays that can occur together cannot be treated as mutually exclusive. Check the new plan and the participants’ release and handover rules; moving reserve into one place does not make it available before every earlier commitment. Keep or restore local protection where the joint arrangement cannot protect that earlier result.

For known deterministic conditions, the feasible schedule can be enough. To protect against a stated extra hour of review, add that hour to the appropriate operation and recompute the plan. This answers the scenario without inventing its probability. A service-probability claim needs the corresponding duration and dependence model; OPS.10.1 supplies that construction.

After inserting protection, recheck resource and calendar feasibility. Moving a feeding operation earlier can take another task’s reservation. Keeping two hours before final delivery does not make those hours usable before an earlier calendar closure. Do not allocate the same margin to several independent promises without checking their combined delay.

Return the selected target times, reserved intervals and response to reserve consumption to OPS.8 for release and protection. OPS.7 uses the delivery consequences for priorities; use OPS.14 when the start policy or its economic justification depends on a financial comparison.