OPS.10.2:4 - Solution
Recover the recipient’s result and deadline and the operations needed to deliver it. Identify what enables each operation, which resources it occupies and the usable calendar windows. Seek a feasible schedule or a sufficient obstruction. A failed placement leaves other allowed schedules open unless a bound or complete search rules them out. For a feasible plan, calculate the start windows and delivery reserve needed to compare early work, postponement or protection. When a condition changes, retain completed facts, reconsider the affected dependencies and resource competition, and return the consequences to whoever can set priorities or authorize release.
OPS.10.2:4.1 - Recover the delivery question and remaining work
State the result that must be available, its deadline and its waiting origin. An internal completion can precede transport, approval or receiving acceptance. Include those operations when the promise needs them.
Separate hard requirements from preferences. “Meet all three dates” asks for feasibility. “Finish the last order as early as possible” minimizes the last completion. “Obtain the first result sooner” can prefer a different order. If competing recipients cannot all receive their earliest possible result, OPS.7 supplies the priority and commitment choice.
For each remaining operation, recover its readiness event, required predecessors, duration or bounded scenario, eligible resources, and whether it can be interrupted. Include setups, transfers and known return work when they consume relevant time. Retain completed operations and work already under way as facts; estimate only their remaining requirements.
Two orders can require the result of one inspection. Reserve the inspection once when one execution meets both orders’ acceptance conditions and the result will be ready for each. If both units require a test, determine which work must be supplied for each. One permitted batch can test both units provided each receives acceptable evidence in time. Reserve separate performances when the terms or the operation require them, and count genuinely shared setup or equipment time once. An execution that requires two people together occupies time on both calendars. Carry these occupations into the schedule below.
Qualify the duration before calculating a schedule. Recover the execution conditions and whether the quoted time includes waiting or deliberate protection against overruns. A protected task commitment is not, by itself, a measure of the time the work takes. Keep work and required waiting in the timing model, and identify protection already included before reserving more time for the same delays. If that split is unknown, obtain a supported estimate or compare explicit duration scenarios; cutting every quotation by the same percentage does not recover the missing basis.
Keep the finite work list at the detail the decision needs. If a task requires an operator only during loading, recover that phase without decomposing every machine movement. If an uncertain duration affects feasibility, the scope of the service claim or a choice between plans, compare supported bounds or obtain that particular input. A full event history is unnecessary when the supplied conditions already settle the schedule.
OPS.10.2:4.2 - Construct precedence, occupation and calendar conditions
A precedence relation states which event must occur before another operation may begin. For a continuous operation i of duration p_i, finish f_i equals start s_i plus p_i. A finish-to-start relation from i to j with required delay l requires s_j >= f_i + l. At a join, every required predecessor must satisfy its relation. An actual partial handover can use an earlier event, provided the downstream work can use that partial result.
Resource sharing adds a different condition. Two operations requiring the same exclusive resource cannot occupy it at the same time. Their order is a choice unless the operation already fixes it. For a pool, check how many eligible members are needed simultaneously; one free but unqualified person does not supply the required capability.
Recover each occupation separately. A machine may hold an order for three hours while its operator is needed only in the first hour. Represent the machine interval and that operator interval with their common start. Apply each resource’s capacity and calendar to its own intervals. Use half-open intervals, including the start and excluding the finish, when a resource can pass immediately to the next operation.
Distinguish three calendar conditions that require different placements:
- A continuous occupation must fit wholly inside an available window.
- Work that may pause can accumulate processing across open windows, with any restart cost included.
- A machine may continue through an operator’s absence when that phase needs no attendance.
A rule allowing an operation to start during working hours does not establish that its later occupied hours are available. Where several resources are needed together, find a window in which their required occupations are jointly possible.
Check that the precedence relations can be satisfied. A finish-to-start cycle with positive total required duration and delay is an obstruction. When the work actually revisits a station, represent the later visit as a later operation rather than requiring one operation to precede itself.
MMP.10 supplies the joint formulation. Keep the operational reason for a condition recoverable: actual precedence, chosen resource order, calendar closure, admission policy or deadline. A chosen order can be reconsidered without pretending the technological route changed.
OPS.10.2:4.3 - Place the work and distinguish the resulting conclusions
For a small case, start with operations whose required predecessors have been placed. Choose an eligible operation, find its earliest jointly available placement after readiness, reserve the required intervals, and continue. Several reservations may be made within one long machine operation when its attendance phases allow other work.
At a resource conflict, compare the competing orders. A near deadline or a long downstream continuation can guide the first attempt. Preserve alternatives when that first attempt fails or gives an inadequate result. Inserting work into a gap, leaving a resource temporarily idle, or changing an uncommitted order can permit a schedule that a simple dispatch rule misses.
Once the relevant orders are fixed, calculate the earliest times consistent with them. With continuous availability and finish-to-start relations, each start is the maximum of its readiness and predecessor finishes plus their required intervening delays. Chosen resource-order relations also contribute predecessors. For partial attendance, connect the occupied phases, not the finish of an unrelated unattended phase. With calendars, move each proposed occupation to the next jointly permitted window and propagate the resulting finish.
Check the complete candidate against every required operation, precedence, occupation, calendar and completion event. A feasible assignment is a witness that the modeled work fits; the participants must still have the stated access and capability.
Use cheap necessary bounds before a larger search. A required dependency chain cannot finish faster than its ordered work permits. A resource cannot supply more mandatory occupation than its available capacity in the required window. A continuous operation cannot use several disjoint short windows as one long window. Passing these bounds does not construct a schedule.
Return the actual strength of the result:
| Obtained result | Supported conclusion |
|---|---|
| Complete feasible schedule meeting the dates | Those dates are attainable under the stated conditions. |
| Feasible completion C and lower bound L on the earliest possible completion | The optimum lies between L and C. Equality establishes an earliest completion. |
| Necessary condition incompatible with the deadline, or a complete valid search excluding every permitted schedule | The deadline is impossible within that modeled arrangement. |
| A failed priority rule, restricted sequence or interrupted search | That attempt found no satisfactory plan; other permitted schedules remain unresolved. |
CMP.4 supplies justified search when the operational choices remain numerous. CMP.5 supplies relaxations and bounds. Use an adequate existing bound or schedule. If a specialist must develop one, supply the relevant resource and calendar conditions and the conclusion to establish.
Stop when a suitable plan or sufficient obstruction answers the decision. Continue optimizing when a reachable improvement in the schedule or the bound justifies the additional work.
OPS.10.2:4.4 - Derive time reserve and conditional criticality
First state the event against which reserve is measured. If the proposed final completion is C and its deadline is D, D-C is the plan’s final margin. A negative value shows that this plan misses the deadline; it does not by itself exclude another plan.
For a precedence network with fixed durations, continuous calendars and no binding resource contention, calculate early starts forward and latest starts backward. Start the backward pass from the selected final time T, retaining any earlier hard intermediate deadlines. For each successor, subtract the required intervening delay from that successor’s latest start. The earliest of those bounds and any deadline on the operation gives its latest finish; subtract its duration to obtain its latest start. Latest start minus early start is its total float relative to those targets. Free float is the delay that leaves the successors’ early starts unchanged, including their required intervening delays.
When only the final event governs this calculation, setting T to the earliest final completion identifies zero-float paths controlling that completion. An earlier intermediate deadline can instead give zero float to work protecting that intermediate event; identify which event the result concerns. Using a later final deadline adds delivery margin where other commitments permit it, so an operation on the longest precedence path can have positive deadline float. Several longest paths can exist. Serial operations may draw on the same margin, so their individual floats are not independent allowances to add together.
With shared resources, retain the selected allocations and orders when making the timing calculation. For whole-operation exclusive occupations, add the chosen resource-order relations to the precedence network; its timing is conditional on those orders. For partial occupations or calendars, use the corresponding phase and window constraints. A different allowed order or calendar can change the controlling sequence.
To assess a proposed postponement, hold the stated commitments fixed, delay that start, and refit the affected work. Identify the latest feasible placement or the set of feasible start windows that still meets the protected event. Calendar gaps can make intermediate start times infeasible even when a later window exists. A backward arithmetic pass that ignores those gaps supplies no usable postponement permission.
Call a sequence critical for a stated plan, resource order and target event. Test a claimed critical operation by varying its duration or availability and recalculating that event. A throughput bottleneck limits sustained flow under a workload. A different condition can govern the first result by a deadline. Use OPS.9 to diagnose the constraint on the result in question.
OPS.10.2:4.5 - Choose early work, deferred starts and protection
Compare start policies inside the feasible windows. Starting earlier can reveal problems and retain recovery time. Deferring can avoid aging, premature expenditure or work invalidated by a later input. Retain the recipient’s original waiting boundary in either comparison.
When protection is needed, name the event and disturbance to be absorbed. Choose an internal target earlier than the commitment, or reserve time before a consequential join. Determine its amount from the delay scenario, supported bound or risk model that matters to the decision. A final margin is available time; calling it a buffer adds a policy for preserving and using it.
When several operations protect the same delivery, compare keeping their individual protection with placing protection before the common delivery or a feeding join. Revise the operation estimates and protection together, preserving the required work, intermediate obligations and execution conditions. Size the shared protection for the joint delays it must absorb: delays that can occur together cannot be treated as mutually exclusive. Check the new plan and the participants’ release and handover rules; moving reserve into one place does not make it available before every earlier commitment. Keep or restore local protection where the joint arrangement cannot protect that earlier result.
For known deterministic conditions, the feasible schedule can be enough. To protect against a stated extra hour of review, add that hour to the appropriate operation and recompute the plan. This answers the scenario without inventing its probability. A service-probability claim needs the corresponding duration and dependence model; OPS.10.1 supplies that construction.
After inserting protection, recheck resource and calendar feasibility. Moving a feeding operation earlier can take another task’s reservation. Keeping two hours before final delivery does not make those hours usable before an earlier calendar closure. Do not allocate the same margin to several independent promises without checking their combined delay.
Return the selected target times, reserved intervals and response to reserve consumption to OPS.8 for release and protection. OPS.7 uses the delivery consequences for priorities; use OPS.14 when the start policy or its economic justification depends on a financial comparison.
OPS.10.2:4.6 - Reconstruct the affected remainder after a change
At the current time, retain actual starts, completions and ongoing occupations. Replace the changed duration, readiness, access window, required operation or commitment. Do not restart completed work or shorten an uninterrupted operation merely to recover the former finish date.
Follow the changed operation through both its successors and the resources it shares. A task outside its precedence descendants can still lose a resource window. Include resulting admission changes and downstream joins; widen the affected set until its remaining boundary conditions are unchanged.
Try retaining unaffected reservations and the useful parts of the former plan. Refit the affected work under those commitments. If that restricted repair fails, identify which still-changeable reservation or resource order could matter and compare a broader rearrangement with its coordination cost. Failure while preserving the old order excludes only that restricted repair.
Recompute completion times, feasible postponement windows and protected reserve. Compare them with the same recipient events and deadlines. Report what that comparison establishes, such as a changed start or allocation, reserve consumed, an obtainable operating remedy, a commitment needing reconsideration, or an unresolved scheduling choice. Retain unaffected model and calculation results whose premises still hold.