OPS.10.2:4.1 - Recover the delivery question and remaining work
State the result that must be available, its deadline and its waiting origin. An internal completion can precede transport, approval or receiving acceptance. Include those operations when the promise needs them.
Separate hard requirements from preferences. “Meet all three dates” asks for feasibility. “Finish the last order as early as possible” minimizes the last completion. “Obtain the first result sooner” can prefer a different order. If competing recipients cannot all receive their earliest possible result, OPS.7 supplies the priority and commitment choice.
For each remaining operation, recover its readiness event, required predecessors, duration or bounded scenario, eligible resources, and whether it can be interrupted. Include setups, transfers and known return work when they consume relevant time. Retain completed operations and work already under way as facts; estimate only their remaining requirements.
Two orders can require the result of one inspection. Reserve the inspection once when one execution meets both orders’ acceptance conditions and the result will be ready for each. If both units require a test, determine which work must be supplied for each. One permitted batch can test both units provided each receives acceptable evidence in time. Reserve separate performances when the terms or the operation require them, and count genuinely shared setup or equipment time once. An execution that requires two people together occupies time on both calendars. Carry these occupations into the schedule below.
Qualify the duration before calculating a schedule. Recover the execution conditions and whether the quoted time includes waiting or deliberate protection against overruns. A protected task commitment is not, by itself, a measure of the time the work takes. Keep work and required waiting in the timing model, and identify protection already included before reserving more time for the same delays. If that split is unknown, obtain a supported estimate or compare explicit duration scenarios; cutting every quotation by the same percentage does not recover the missing basis.
Keep the finite work list at the detail the decision needs. If a task requires an operator only during loading, recover that phase without decomposing every machine movement. If an uncertain duration affects feasibility, the scope of the service claim or a choice between plans, compare supported bounds or obtain that particular input. A full event history is unnecessary when the supplied conditions already settle the schedule.