FIN.9:4.2 - Compare value under interactions and dated constraints
Bring values to one date, currency, claimant and compatible tax and risk grounds. Different components may have different required returns. Value them on their supported bases before combining present values; forcing their cash differences through one convenient rate can change the economics. If selecting the combination changes financing terms or risk treatment, recalculate those affected values through FIN.5.
For a proposed combination, trace how the projects together affect cash against the baseline. The joint price or capacity requirement may already answer whether the package fits. If the projects can also stand alone and the decision depends on the effect of combining them, subtract the sum of their separate incremental flows from the combined flows to isolate the interaction. Shared setup, overlapping customers and competing use of capacity can change that difference. If a project has value only as part of the combination, value that whole without inventing a stand-alone business.
Map the resource use and money needed when each constraint binds. Include initial commitments, later investment, collateral, working capital, operating capacity and financing access. A project with a modest initial outlay can absorb the capital needed by another one next year. A positive annual ending balance can conceal an earlier shortage. FIN.2 supplies the dated cash requirement; operating practice supplies the capacity account.
For a small set, enumeration is often enough. Include the empty choice when feasible, singles and combinations; remove only those excluded on established grounds; compare the whole values of those remaining. A useful dominance conclusion requires one alternative to be no worse on every relevant consequence and constraint and better on at least one, under the stated conditions. Where a capital limit is a hard feasibility condition and NPV is the sole objective, the higher NPV ranks first among feasible complete alternatives. Where unused capital has another valuable use, include its consequences in the whole comparison. If preserving capital is an additional objective, compare that trade-off explicitly.
A larger problem can use a constrained optimization model. Let a binary selection variable represent an indivisible project. A mutual exclusion restricts two selections to at most one; a prerequisite requires the dependent selection to imply the prerequisite. Apply each resource constraint at the dates and for the amounts that would be required. Interaction terms or scenario-dependent choices need their own representation. Inspect what the objective and constraints mean before accepting the computed optimum; a solver cannot find an alternative omitted from the model.
For divisible independent investments with one initial capital limit, linear scalable values and no other constraints, ranking value per unit of capital can construct an allocation. State the chosen profitability-index definition; conventional PV-of-receipts divided by initial outlay and NPV divided by initial outlay differ by one for that simple flow pattern. Indivisibility, minimum scale, interactions or future funding constraints can defeat the ranking. A large ratio is not evidence that the leftover budget can be usefully deployed.
A financing constraint can be either fixed for this decision or open to a worthwhile construction. If useful combinations are excluded by the current funding set, use FIN.10 to develop missing terms or FIN.23 to change group financing when that could improve the choice. Add each proposed arrangement’s cost, claims and conditions to its own combination. Continue to distinguish a conditional proposal from a presently available alternative; obtaining more finance cannot rescue an investment whose full consequences remain unattractive.