EAM.10:5 - Archetypal Grounding
EAM.10:5.1 - A shared operation changes the comparison
Consider a separate constructed service requirement. Two interventions P and Q together and a different complete solution Z are both qualified to supply it over the same horizon. P or Q alone is insufficient. Their subsequent operating, ending and other material consequences are equal; all different costs are payable now in €million, and funding is sufficient for either whole solution. Thus their initial cost difference decides this bounded comparison.
P costs 2.0, including 0.2 mobilization, and Q also costs 2.0 including 0.2. Z costs 3.9. The operating practitioner establishes that P and Q can be performed sequentially during one qualified visit, using one 0.2 mobilization. Required service remains supported during the work; the shared visit incurs no additional consequence outside the supplied account.
| Whole choice | Separate estimate | Joint adjustment | Comparable cost |
|---|---|---|---|
| P and Q with one mobilization | 4.0 | −0.2 | 3.8 |
| Complete solution Z | 3.9 | 0 | 3.9 |
The whole P+Q estimate is 1.8 + 1.8 + 0.2 = 3.8. Sharing a mobilization removes 0.2 from the estimate for doing P and Q separately. Compared with Z at 3.9, the feasible joint plan saves an estimated 0.1 and can be chosen on that basis. To report the eventual expenditure, recover the work and charges incurred. To report a realized saving, also establish what the relevant alternative would have cost for the same service.
Suppose incompatible access windows require two visits and two mobilizations. P+Q returns to 4.0 and Z becomes cheaper at 3.9. If instead the proposed shared visit fails the service condition, remove that arrangement as ineligible and compare any qualified two-visit arrangement with Z. Reducing its price cannot repair the lost service. EAM.11 establishes which visit arrangement is feasible; EAM.10 uses its consequences.
Before applying a saving to CityWater’s station jobs, establish what work they could share, whether service would be maintained, and how their joint costs would change.
EAM.10:5.2 - The sixteen supplied CityWater combinations
The common CityWater application supplies four two-option choices. Initial capital must not exceed €8 million, initial operating expenditure €0.60 million, annual operation €3 million and the available team/outage time twelve days. All amounts and eligibility results are constructed.
FFMK—refurbish A and B, modify C, continue D—uses €7 million capital, €0.50 million initially for operation, €1.85 million annually and eight days. Its present cost is €14.592284 million, the lowest among the declared eligible combinations. EAM.Application:2 shows all sixteen combinations.
Adding D replacement while retaining the other choices gives FFMR: €10 million capital and lower present cost of €13.080344 million. It is infeasible at the €8 million allocation. Switching C to leased service permits D replacement within capital, but FFLR costs €15.350138 million overall.
If the funding board raises capital to €10 million, FFMR becomes preferred. If D continuation instead loses its engineering qualification, FFLR becomes preferred at the original limits.