SYSE.6:5 - Worked Case: Architecture Decision for the Heat-Pump Plant Controller
Engineers using SYSE.5 have developed two alternatives for the same occupied-building heat-pump plant.
In A, local unit controllers carry protection and normal regulation while a supervisor sends bounded
set-points. B adds thermal storage and tariff scheduling; its local controllers retain protection and regulation.
The decision is which architecture should guide engineering of configuration HP-2 for the next three
heating seasons. The architecture board is the decision subject. Its authority for this choice comes from a separate
project authorization. The assignment and decision record do not confer that authority.
Continue the SYSE.5 proposals with additional stipulated design inputs: a thermal/hydraulic account
and a compatible sensing and control arrangement. These are premises of this worked case, not reported plant
results. If the sensor-variant conflict in SYSE.7 remains open, follow that return before relying on the
storage comparison below.
Both proposals use the same building heat-demand and weather envelope, comfort requirement, communication-loss condition, installation window and budget. Compatible unit results and design analyses support both at the scope of the architecture commitment; whole-plant qualification is required before operation. Seasonal energy and storage-cycling claims remain unresolved as shown below. Layout and supply estimates leave both options within the window and budget, with the required maintenance access.
After protection and comfort, the building owner gives priority to less installation disturbance and a smaller added maintenance burden. Peak-period flexibility is desirable but is not a current requirement. The board compares the complete arrangements under those conditions:
| Decision-relevant consequence and basis | A — local regulation with bounded supervision | B — storage with tariff scheduling |
|---|---|---|
| Protection and comfort under the shared envelope | Uses the qualified local protection and the existing heat-delivery path. The design analysis supports the required comfort response. | Retains the same local protection. The design analysis includes the storage charging and discharge modes needed for comfort. Neither option gains preference by dropping the protection condition. |
| Installation and maintenance burden in the stipulated plans | Retains the heat path and adds supervisory connections and configuration. It needs fewer site changes and no storage-loop servicing. | Adds a tank, pump, valves, sensors and charging controls. The layout allows access, but installation and later servicing cover these additional parts and modes. |
| Response during a two-hour utility peak | Can adjust set-points within the comfort envelope, but the stipulated heat balance does not support a two-hour compressor stop at the declared cold-weather load. | A design-stage heat balance supports delivery from the charged store during that stop, including usable stored energy, discharge rate and losses. This is model support for the declared conditions, not an observed operating result or zero electricity use by the whole plant. |
| Seasonal energy, cycling and economic consequences | Peak-period compressor use remains. Comparative seasonal consumption and total cost are not established. | Tariff scheduling could move purchases out of the peak period; storage losses and charging cycles also matter. The available comparison does not establish a seasonal energy or total-cost advantage. |
| Continuing change | Storage can be added later through reserved interfaces, but that would require another physical alteration and qualification. | Storage flexibility is developed now, at the cost of the added equipment, control modes and their continuing configuration and evidence burden. |
Present choice. The board selects A. Both proposals meet the conditions needed for this bounded commitment, and A is better on the owner’s stated priority. B’s supported peak-shifting possibility does not override that priority while flexibility remains optional and its seasonal economic advantage is unknown. No aggregate score is needed. The board accepts A’s lack of the modeled two-hour shift, continued exposure to peak-period purchases, and the possibility of a later retrofit. It does not claim that A has the lowest lifetime cost.
The resulting ArchitectureDecisionRelation@Project fixes these structures:
- local protection remains within each unit boundary and does not depend on supervisor or utility communication;
- supervisory set-points stay inside declared unit operating envelopes;
- plant-state and command interfaces carry units, timestamps, quality, validity, fallback, configuration and effectivity conditions;
- a later storage branch enters through the declared thermal, control, configuration and assurance interfaces.
Algorithm choice, hardware supplier, detailed state estimator and user-interface design remain open
provided they preserve those constraints. The controller and integration teams use the constraints while
shaping controller, bench, installation and integration Work with SYSE.3. Configuration and interface-version
Work uses SYSE.13; utility-signal authority and service conditions use SYSE.18. Model and trial results are
assessed through SYSE.10, and assurance through SYSE.4. Each receiving practitioner applies the relevant
Method to produce the needed result; the architecture decision supplies constraints and questions.
Changed premise. Suppose the utility contract now requires that same two-hour compressor stop while the building’s comfort requirement remains. The accepted flexibility loss is no longer admissible. Reopen the A/B choice: with the other stated premises still current, B’s heat balance supports selecting it for further engineering, while A’s does not support the new requirement. The board can make a new decision for the remaining horizon; this does not qualify B for operation. Preserve the local protection constraint and still-applicable unit results, and return the storage, charging-control and integration questions to their receiving work. If the relied-on storage calculation or installation premise fails, reopen that unsupported branch instead of treating the new contract as proof that B works.
If the tank price falls, the board checks whether that changes the burden comparison or the owner’s priority before deciding whether to replace A. The available evidence does not establish seasonal savings. Communication-loss failures, comfort or cycling guardrail crossings, changed utility-signal semantics and material installed divergence also retain their named return to the affected architecture question.
After integration, compare the actual installed Systems and relations with the decision content. Different wiring, fallback or control allocation is an implementation divergence even if the architecture record was left unchanged. The decision, its later supersession and evidence of the obtaining plant configuration remain separate.