SYSE.20:5 - Worked Case: Power-Converter Integration

This constructed case separates an observed diagnostic account from a plan for the next run. Its durations, resource commitments and engineering qualifications are stipulated inputs, not measured performance claims about power-converter projects generally.

SYSE.20:5.1 - Recover the failure before making the plan

A team prepares an integration recommendation for a power converter. A separate decision determines whether to authorize release. The team records the following Work in its diagnostic run:

Work occurrenceInterval on the run clockDirectly relevant relation
physical-model correctionminutes 0–25overlaps simulation during minutes 10–25
numerical simulationminutes 10–35uses named model editions and depends on a compatible solver service
rig reconfigurationminutes 30–50must finish and receive rig-release authority before closed-loop test
closed-loop testminutes 50–75uses the released rig and named converter configuration
evidence reviewminutes 70–90begins before test completion; its final inference needs the test evidence

The provider performs solver-service recovery during minutes 32–43. That Work remains separately identified; its overlap does not make it a constituent of the project Work. Earlier laboratory training is neither simultaneous with nor part of this run. Evidence of capability under the relevant conditions is needed; the training date establishes only temporal order.

Each occurrence has a performing Agent and enacted Method, with assignment and authority recovered where the claim uses them. The five intervals establish temporal relations, not that five Methods compose one Method. The rig-release condition and solver-service dependency require their own grounds.

The engineers connect three descriptions: the Work relations; the converter, control board, power stage, rig, load bank and platform under their subject and service relations; and the model editions, solver configuration, simulated results, measured traces and criteria under their representation-use relations. These are the structures needed here. The conflict is that simulation starts on a changing model and finishes during service degradation. Its output cannot yet support the intended configuration claim. The recorded overlaps answer which work ran together. Checking suitability gives a further result: the recommendation written at minute 90 lacks the evidence needed for use. Neither conclusion requires choosing how to run the work next.

SYSE.20:5.2 - Obtain the inputs that determine possible overlap

For the next run, the lead needs a qualified recommendation for converter configuration C7 by minute 105. The relevant specialists supply these conditions:

Contribution or conditionQualified case input and its consequence
Model and simulationModel correction takes 25 minutes. A qualifying simulation takes 25 minutes on the final model with a compatible solver. No qualified change envelope permits an earlier simulation to stand for it.
Shared providerRecovery finishes no later than minute 43; compatible capacity is reserved continuously after recovery for this run. A health and configuration check is included in admitting the simulation result.
Rig and testRig setup and its release take 20 minutes and depend on already fixed C7 rig instructions, not the unfinished model correction. The test takes 25 minutes after both rig release and the qualifying simulation have become usable.
InterpretationAfter simulation, a two-minute configuration and evidence check interprets its result for this C7 test. Include this work in every alternative.
ReviewThe applicable review Method permits 15 minutes of procedure and available-evidence preparation followed by a five-minute final inference after the test evidence arrives. A review done wholly after the test takes the same 20 minutes.
People and equipmentA modeler, a simulation operator, a test operator and an authorized reviewer are distinct qualified people. One laboratory engineer performs rig setup, the two-minute check and any local-service setup; that engineer cannot do two at once. All have confirmed availability during minutes 0–135, and rig and test equipment remain available through that interval.
Local solver alternativeA compatible local service is already qualified for this use. Setting it up takes the laboratory engineer 15 minutes. Using it transfers configuration, security and validation responsibility to the laboratory and adds two hours of maintenance each week; that capacity and authority are available if chosen. These are current case facts, not consequences of installing software.

The lead’s rule is to meet C7 evidence eligibility, rig and authority conditions, and the minute-105 deadline; among eligible options, prefer lower additional continuing service burden. Setup and interpretation durations are included in the schedules. Other immediate costs are accepted within the lead’s stated budget and do not distinguish the options in this case.

The current unqualified overlap is excluded: its early result lacks the required support. A feasible current arrangement would remain an option, but retaining a failed premise is not the incumbent.

SYSE.20:5.3 - Construct and compare three complete arrangements

First preserve all dependencies in a serialized option A. Then examine each wait: rig setup need not wait for the model or simulation, and the first 15 minutes of review need not wait for test completion. Moving only that independent work earlier constructs B. Finally replace the unavailable shared-service interval with the qualified local alternative to construct C, including the laboratory engineer’s competing setup.

The schedules use the shared provider’s latest qualified ready time. They show completion bounds under the stated durations and availability; earlier recovery may allow an earlier start.

Operation or resultA — serializedB — independent preparation overlapsC — qualified local solver
Model correction0–250–250–25
Local-service setupnonenone0–15
Qualifying simulation43–6843–6825–50
Configuration and evidence check68–7068–7050–52
Rig setup and release70–900–2015–35
Closed-loop test90–11570–9552–77
Review preparation115–13080–9562–77
Final review and recommendation130–13595–10077–82
First usable recommendationminute 135minute 100minute 82
Additional continuing service maintenancenonenonetwo laboratory hours per week

A is eligible as an evidence arrangement but its schedule does not meet the deadline. In B, the test starts by max(20, 68+2) = 70. Review preparation finishes with the test, so the recommendation is ready by 95+5 = 100. Every required result is joined; early review is preparation, not early release.

For C, placing local setup at 0–15 and rig setup at 15–35 avoids simultaneous demands on the laboratory engineer and lets simulation begin when the final model is available at 25. The test starts at max(35, 50+2) = 52 and the recommendation is ready at 77+5 = 82. Reversing those two setup tasks would delay local-service availability to 35, simulation to 35–60, the test to 62–87 and the recommendation to 92. Thus even this small example needs a resource order as well as an information order.

Both B and C meet the deadline. The stated rule selects B because C adds continuing laboratory maintenance. C is faster. If an earlier recommendation had additional value or maintenance capacity were unavailable, the comparison would change. Compared with A, B makes the same qualified result available 35 minutes earlier. Compared with the invalid original run, there is no supported “ten-minute delay”: its minute-90 output never met the same eligibility conditions.

The lead authorizes implementation of B. The project makes the resource reservations and input/update arrangements real, updates the plan and review instructions, and follows the next representative run to its usable recommendation. The provider availability and compatibility requirement can constrain SYSE.12; the resulting project observation can enter SYSE.21.

SYSE.20:5.4 - Change one provider condition and retain the valid work

Before execution, the provider revises its latest ready time from 43 to 60. All other stipulated conditions remain available. At that latest time, B gives simulation 60–85, interpretation 85–87, test 87–112, preparation 97–112 and final review 112–117. Its operations remain technically usable, but this bound no longer guarantees the minute-105 deadline. Earlier observed availability or a tighter qualified bound can change that conclusion; otherwise choose an arrangement that supplies the required guarantee.

C still finishes at 82 under its unchanged availability and qualification premises. The lead can choose it within the stated authority and accept its maintenance burden. The model, rig Method and review split remain usable. If the local service or its continuing support cannot be obtained, C is unavailable. State the provider or capacity commitment that is missing, or ask the deadline holder to decide whether to change the deadline. A request for faster recovery does not establish a new promise.

This is a prospective change. If some Work has already been performed, start from its actual state and remaining resources; the table is not permission to restart its clock or discard still-valid results.

SYSE.20:5.5 - A coupled design question needs an iteration, not just earlier starts

Consider a pipe route whose clearance depends on a bracket position, while the bracket design depends on that route. No ordering of the two final designs resolves the cycle. For a stipulated prototype, the engineers can use a qualified adjustable fixture and a pipe mock-up to test one provisional interface. They select the initial route and bracket setting within the fixture’s permitted range, check the joint fit, and return the measured interference or clearance to both designs. The fit criterion and fixture qualification come from the assembly specialists.

A successful joint fit permits the specified final-design step; an interference returns to the affected geometry. If the needed movement exceeds the fixture’s permitted range, its qualification no longer supports that trial: obtain another means or revise the proposal. The fixture work may be reversible while drilling final holes is not. Keep drilling behind the required fit and authorization condition.