OPS.8:4.3 - State what each buffer protects
If the service needs protection, identify what must be protected and a quantity that represents it.
| Arrangement | What its policy controls or protects | Useful quantity |
|---|---|---|
| ready-work buffer before a selected service | service continuity during replenishment delay | eligible service load, related to the resource’s operating calendar |
| inventory reserve | availability of specified material under replenishment and consumption uncertainty | usable quantity by material, location and condition |
| capacity reserve | response or recovery when load or availability changes | usable resource time with the necessary capability and access |
| limit on started items | congestion and exposure from concurrent unfinished matters | items under an explicit start/finish boundary, with load differences retained |
For the selected arrangement, state the shortage or disturbance, the consequence of failure, who replenishes it, what consumes it, and which signal calls for replenishment or another response. A customer’s commitment has its own parties and conditions; it does not automatically put the item in a protective buffer.
Work backward from the next shortage: when must replenishment become eligible, how long do recognition, request, authorization, supply and receiving checks take, and what other work uses the same people or resources? Choose a trigger that leaves that whole response available. For continuing service, also recover the quantity supplied per request, the earliest permitted next request, any overlap limit and the supplier’s capacity. Follow successive consumption and replenishment events: the available eligible load must cover consumption until the next replenishment is eligible for use, and replenishment must sustain the required pace. More initial stock can cover a finite gap but cannot correct a continuing supply deficit. Distinguish material ordered, delivered and actually ready. A late-response signal needs a permitted alternative, such as different supply, protected capacity or an explicit service revision.