OPS.21:5.1 - Derive a repair aim before negotiating resources
This constructed cooperative has twelve identified customers whose equipment could usefully return to service this month. Five have booked; seven have received qualified offers, and the available demand evidence supports a forecast of three further acceptances. The expected number of orders is eight. How many of the seven will actually order, and which customers they will be, remain open. All twelve needs are suitable for the cooperative’s standard repair; each customer retains the choice to accept or decline. Restoring useful equipment, with customer acceptance and no omitted quality work, is the receiving result.
The team considers eight, ten, twelve and fourteen accepted repairs. Eight is the forecast of orders. The number of completed, accepted repairs also depends on timely work and acceptance. Ten accepted repairs would serve two more needs than eight accepted repairs and would use 36 hours. Whether the base arrangement can deliver ten in time also depends on when orders arrive and when the work and acceptance can be completed. Twelve would meet the complete known opportunity if all customers accept and the work can be supported. Fourteen has neither identified demand nor a way to achieve additional useful work in this case. The team provisionally selects twelve as a conditional ambition, with prompt clarification of the seven offers as its first action. It retains eight as the forecast of orders. If customers decline because repair no longer serves them, manufacturing a repair sale would defeat the purpose; reconsider the affected aim.
The base arrangement supplies 36 usable hours after protecting continuing service. Setup needs six hours and each standard repair three. Eight repairs need 30 hours, ten need 36, and twelve need 42. One obtainable extra block of eight hours would give 44. These totals test the labour requirement. To promise dated repairs, place the work in available windows after the orders arrive and allow for the agreed acceptance. The ambition exposes a resource decision; it does not establish that the block is staffed or funded. The dated financial comparison shows that twelve repairs with this block would leave 20 less in closing cash than ten using the base provision. The cooperative decides that serving the two additional customers is worth that difference, provided the funding needed before customers pay is obtained and continuing service remains protected. This explicit judgement sustains the ambition; if the difference were not worthwhile, ten would be a reasoned alternative. The resource holder still has to authorize and provide the block before anyone promises the additional work. The connected repair example (Engineering.Reference:7) carries this result through provision, cash, changed work and assessment.