OPS.14:5.5 - The deferred slot displaces an accepted job

Change :5.1’s no-displacement premise. The month-2 slot is now the only available way to complete previously committed job J on time. J would bring 1,100 at the end of month 2 and needs 200 of avoidable consumables before its service. The same 300 salary is paid in both alternatives, even if J is not performed. That unchanged payment has separate reserved funding; the 500 allowance in :5.1 remains available for the extension’s differing payments. No other contribution uses the slot. All figures use the earlier common horizon and currency.

Completing the third package now leaves the slot for J. Deferring it uses that slot and loses J’s receipt while avoiding J’s 200 consumables. For this comparison, J’s recipient has authorized cancellation without penalty if the slot is withdrawn; without that permission, the deferral is not an admissible choice merely because its cash total is attractive. Preserve the actual commitment until its agreed cancellation takes effect.

Cash component through month 2Complete the third package now; perform JDefer the third package; cancel J
Third package, unchanged from :5.1+100+800
J receipt less its avoidable consumables1,100 − 200 = +9000
Salary retained in both alternatives−300−300
Total for these components+700+500

Now minus defer is +200, so the financial preference reverses in favor of completing now, conditional on feasible service and funding. The same answer is the earlier −700 difference plus 900 of foregone J cash. A reported J contribution of 600 that already deducted the retained salary would understate the displacement by 300. The table includes J’s lost receipt and avoided consumables once; subtracting a further 900 “opportunity cost” would count the same loss twice.

The earlier 300 advance-funding gap for the immediate option remains. J’s later 200 payment also needs funds when due; the month-end receipts do not pre-fund it. If funding or cancellation authority is absent, return that constraint before acting. If J’s receipt is only 800 with the same 200 avoidable payment, its foregone cash is 600 and now minus defer becomes −100: the financial preference returns to deferral. This is a changed demand/payment premise, not a salary saving.