OPS.10:5 - Archetypal Grounding
OPS.10:5.1 - PumpWorks: fit, reserve and a deferred package
In this constructed extension, four eligible test packages each require two consecutive rig-hours, including their normal setup, under the current estimate. In the next eight-hour horizon, this operation has access during hours 0–6; hours 6–8 are currently reserved for another use. This gives six continuous usable rig-hours. Permission and required configuration for the tests are current; release authority and SafetyQuestion-S19 remain separate.
The initial load is eight rig-hours, so all four packages cannot fit the six usable hours even before uncertain recovery. More ready packages or a larger buffer cannot remove that deficit.
For comparison, assume one adverse scenario: one of the planned packages needs a single consecutive two-hour repeat, after which it passes. The failed attempt is identified on completion and its repeat can run next under the current test conditions. This is a supplied scenario, not an estimated failure probability. The resource owner can offer hours 6–8 to this operation through a separate access and cost decision that accounts for the displaced use.
| Option | Usable rig-hours | Planned packages | Explicit reserve | Accepted test packages without repeat | Accepted packages in the one-repeat scenario |
|---|---|---|---|---|---|
| current access, plan two | 6 | 2 | 2 | 2 | 2 |
| current access, plan three | 6 | 3 | 0 | 3 | 2, with unfinished load returned |
| extra access, plan three | 8 | 3 | 2 | 3 | 3 |
| extra access, plan four | 8 | 4 | 0 | 4 | 3, with unfinished load returned |
In the comparison of rig time, both eight-hour options have room for at least three accepted test packages in either stated scenario. Planning three and reserving two hours completes every admitted package in both. Planning four can deliver four without a repeat and leaves one unfinished if a repeat is needed. With six hours, planning two leaves the two-hour repeat available even for the last package. Planning three uses all six hours before any repeat and can leave one of those three unfinished. Compare the cost of extra access, the displaced commitment and the consequences of admitting work that may return unfinished.
If every admitted package must finish in either scenario, three packages and a repeat fit into eight rig-hours. Admitting three also requires qualified relief, incident coverage, recovery, funding and authority for the extension. With those conditions established, admit three and refer the fourth package to OPS.5. In the current case qualified relief is unavailable. Retain two starts and the two-hour reserve, even if extra rig time is offered. Send affected commitments to OPS.7. Any three admitted packages could need eight hours under the stated repeat condition. Return the remaining demand and any existing commitments for authorized disposition.
More than one repeat, a longer repeat, changed configuration or another loss reopens the comparison. A passed test package still does not settle the release decision for R42.
OPS.10:5.2 - Equal total load, different waiting
One continuously available server processes four one-hour jobs. There is no setup, failure, other resource or initial backlog.
| Scenario | Arrival times in hours | Start times | Waiting times |
|---|---|---|---|
| one burst | 0, 0, 0, 0 | 0, 1, 2, 3 | 0, 1, 2, 3 |
| one job per hour | 0, 1, 2, 3 | 0, 1, 2, 3 | 0, 0, 0, 0 |
Both consume four server-hours and finish the last job at hour 4. If the criterion is completion within two hours of arrival, two of four jobs meet it in the burst scenario and all four in the second. The difference follows from the stated arrival scenarios.
Measure arrival-to-completion time from the actual arrival. If a job waits for admission, starting its clock at admission omits that wait.
OPS.10:5.3 - Nominal beds and qualified capacity
A hospital’s bed count is not the capacity for every care requirement. The receiving question may depend on the supplied clinical class, staffing qualification, equipment, cleaning readiness, access and synchronized availability.
Use the applicable clinical and staffing results to compare arrangements and state the resource-time or scenario result. If a required qualification is missing, identify which service capacity remains unresolved and the evidence or decision needed to establish it.