MNT.Application:1 - APP-MNT-01 — PS17: advice, selected intervention and return to use

The constructed case begins on 18 September 2026 with rising bearing-related vibration in PumpTrain-PS17-B, configuration C41. DistrictHeatingOperation-East supplies a qualified capacity result for the stated horizon: its agreed reduced-capacity operation can last four hours under the specified demand and fallback conditions. That operating contribution is the result exchange also identified as XRI-09.

The requested first result is a replacement recommendation. The planner bounds the unit and duty, uses the failure evidence and condition interpretation to establish which claims they support, and compares the responses. The available evidence is sufficient for the planner to recommend a replacement. The long-term cause remains open.

The replacement needs the case’s specialist applicability/certification return for the spare. MNT.5 identifies that unmet condition. The recommendation is complete, while replacement cannot start. The team may prepare compatible information, tools and available support without consuming the protected outage.

In the extended branch, the specialist return arrives and the intervention is selected. MNT.7’s whole-outage calculation includes shutdown and isolation, the intervention, controlled testing, final restoration, return of control and explicit contingency. The resulting 225-minute plan fits the four-hour bound under the constructed estimates. Its calculation and delay branch are in MNT.7; the plan is not a time promise for an unknown pump.

MNT.8 guides authorized personnel in establishing the required protection and permission. If an uncontrolled shared energy path is found, the protected work does not start and the arrangement returns for a competent revised decision. The earlier advice remains complete.

In the performed branch, MNT.9 guides the team in recording removal of bearing R551 and installation of compatible bearing R607. Configuration C42 identifies the resulting installed arrangement under the same approved design basis. MNT.12 preserves the connection between those events and the earlier C41 history.

Using MNT.10, the verifier establishes that C42 meets the immediate duty within the stated operating and measurement conditions. Under the hand-back arrangement, the receiving operator reconciles the returned state and takes control. The authorized operating decision permits the stated duty. A successful function test does not automatically establish that permission or an untested broader duty.

Long-horizon recurrence remains unresolved. The local repair and test have their stated use. For a programme decision, use MNT.13 to establish which installations share the failure, response and support conditions that made this intervention appropriate, or use independent grounds for the wider choice. For a claim that further shifts adopted this way of working, MNT.16 connects the proposed change to what those shifts actually did. Neither further inquiry is required for the original recommendation.