MNT.2:5.2 - Construct a condition-response timing candidate
In a constructed case the warning is at least 8 hours and the subsequent response takes at most 5 hours, including its allowance. With observations every 4 hours, suppose an admissible history has a 4-hour wait, a 5-hour response and an 8-hour warning. Completion takes 9 hours on that history, so this policy cannot guarantee a timely response. With observations every 2 hours the corresponding upper bound is 2 + 5 = 7 hours, sufficient throughout the stated range. Compare the burden of more frequent observation with the cost of shortening the response.
Keeping the four-hour schedule can also be justified under different operating conditions. Suppose the only possible pairs of wait and response are (4, 4) and (3, 5) hours. Both finish in 8 hours, although the separate maxima still sum to 9. Conversely, if the two-hour policy can incur a 6.5-hour response after a full 2-hour wait with only 8 hours of warning, that history defeats its earlier guarantee. A revised upper estimate of 6.5 hours alone leaves that question open. Reconsider sampling, support or another permitted policy using the histories the equipment and service arrangement admit. The applicable operating permission still governs use.