MNT.10:5 - Archetypal Grounding
For the extended constructed PS17 case, the tested installed configuration is C42, with the bearing replacement recorded in MNT.9. The following values are invented to demonstrate a comparison; they are not pump acceptance limits.
The case’s agreed immediate-duty basis requires at least 20 litres per second at a differential pressure of at least 150 kilopascals during a 30-minute representative run. Its supplied acceptance rule is simple comparison of the reported values with those limits, using an already qualified measurement basis for this range and duty. The premise includes a prior assessment of calibration and measurement uncertainty, with the resulting decision risk accepted for this limited claim; it does not assume zero uncertainty or make simple comparison suitable for every use. Instrument drift or changed measurement conditions that invalidate that assessment reopen the comparison.
Under those supplied conditions, the constructed observation is 20.8 litres per second at 154 kilopascals throughout that run, with the applicable equipment-specific condition checks also satisfied: 20.8 exceeds 20 and 154 exceeds 150 under the stated rule. The 45-minute test allowance in MNT.7 includes this run and its controlled transitions.
Those observations establish the immediate-duty result. A winter-peak claim would need a relation covering that load or further evidence there. An as-new lifetime and elimination of the recurrence mechanism each need different engineering grounds. The operator receives that scope explicitly.
Suppose a different order requires each of two outlets to receive at least 9 litres per second throughout the run. For this decision, suppose separate evidence establishes a lower bound of 20.8 litres per second on actual total delivery throughout the run. All delivered flow goes to the two outlets, and a total of exactly 20.8 is possible. Without further restrictions, a split of 10.4 and 10.4 would meet the requirement, while 12.8 and 8.0 would fail it. If the installed arrangement also limits each outlet to 11.5 throughout the run, the other receives at least 20.8 − 11.5 = 9.3. Then both meet the requirement. Without that upper bound, use other applicable delivery evidence or identify the open question. The original pump-duty assessment used its own acceptance rule.
If the loaded test instead reaches only 18 litres per second, the performed bearing replacement can still be correctly recorded while the required functioning claim fails. The team returns to diagnosis or the relevant engineering question. The 18-litre-per-second result remains below the required 20 even if the test is marked complete.