KCAE.COMPOSE:4.4 - Check joint constraints and scheduling

Collect the resources shared across the whole: a person, permission, device, context window, budget, time interval, data store or physical capacity. Add simultaneous demands where addition has the right meaning; do not add incomparable quantities. Check global conditions as well as pairs.

For CedarBench’s proposed batch of three exports, the three jobs each reserve 2 GB and the cache has 5 GB. Every pair needs 4 GB and fits. The three simultaneous reservations need 6 GB, which exceeds capacity. A schedule with two concurrent exports followed by the third resolves the cache conflict, provided the first pair releases its reservation. It can still violate a deadline. If each export needs ten uninterrupted minutes and all three must finish in a fifteen-minute window, each must start by minute five. All three reservations would overlap before minute ten. To meet that order, obtain a different resource arrangement or an authorized change to the work or deadline.

Check interference between activities. Two methods may change the same source, require incompatible configurations or depend on the same observation. Include transition and cleanup work. One feasible schedule can complete the design for this batch. To promise the service across requests, bound the demands of the batches it admits, including overlaps. If the scheduler can defer work, establish which requests, releases of capacity and deadlines it can see before assigning the next export, and which changes it is authorized to make. Its choices must work for every admitted situation still possible on that information.

Consider a ten-minute serial work window. The receiving operation B takes four minutes and requires result R. Candidate A obtains R in nine minutes. A followed by B takes thirteen minutes and fails the window. Preserve B and its unsupplied need; search for another way to obtain an equivalent R in at most six minutes, including the joins and preparation. Candidate C supplies the same R under the case’s source conditions in five minutes, so C followed by B takes nine and fits. Searching for another supplier produces a feasible alternative. Whether C is best remains open.

If a new source edition makes C take seven minutes, reopen the partial arrangement whose feasibility used that estimate. C+B now takes eleven minutes. Retain B’s still-valid contribution, seek another supplier or a permitted change of schedule, and return the unsatisfied window if neither is available. Do not reuse the earlier nine-minute judgement merely because the method names stayed the same. The durations in this example are constructed assumptions, not measurements of a deployed system.