GOALS.Reference:2.2 - Joint conditions and useful partial results
Three teams each need one specialist this week. If their required work occupies the specialist for 12, 10 and 10 separate hours, 24 usable hours leave eight uncovered however the work is ordered. Check whether the same performance could meet more than one team’s terms. Count it once where it does. Then place each remaining use in time against continuing work and each recipient’s deadline. Moving eight hours out of this week helps only if the later provision and the receiving dates permit it. GOALS.3 uses these findings to compare the available undertakings.
A partial result can still be useful: a completed investigation can allow a decision while implementation remains unfunded; several completed refunds can benefit their recipients while other cases remain open. State what the evidence establishes and what the receiving work still needs. The criterion for stopping the current task is the result it was assigned, including its actual conditions. A broader development programme may continue through newly attainable questions after that task ends.