FPF.Reference:16.9.10 - 10. Apply sensitivity without rewriting past Work

If signed supplier pinout is available at D-21, the prospective choice reverses to A before integration. A then reaches the target slot with one final board and avoids the provisional board, later signed-delta preparation, and post-entry recovery exposure. B2 remains only if another named conflict justifies its extra branch.

The changed input affects the prospective decision. If B2 or recovery Work has already occurred, preserve what was performed, its conditions and the evidence used at the time.