ECO.1:5.1 - A cheap plan priced in internal credits
Suppose the repair depot can buy a compatible part for €90 delivered this week. Its spreadsheet prices an internal job at 40 machine credits plus €30 for material. Credits allocate booked machine time. They do not buy more machine time, and the machine has no slot this week. Treating a credit as one euro therefore leaves the apparent €70 plan unsupported.
A nearby provider offers the machining this week for €65 with €30 of depot material. If fit and warranty are equivalent, the two available routes cost €95 and €90. If no matching machining offer can be found, the internal job still lacks a machine slot. Recomputing its allocation does not supply one.
The 40 credits can still be used for their scheduling purpose. Use euro terms for the monetary comparison and capacity evidence for this week’s availability.