EAM.Application:2.1 - When the demand basis changes
The sixteen combinations cover the supplied North wet-season requirement of 1,100 m³/h. Suppose a later demand forecast puts a peak at 1,250. Establish when demands coincide and how the service commitment treats that peak (EAM.4). Either option for C adds 200 to North’s existing 1,000. On those premises the whole district can supply 1,200. The gap of at least 50 excludes all sixteen combinations if service at 1,250 is required. If 1,100 remains the obligation, the forecast identifies an exposure for the service owner to assess under the agreed risk criterion.
When the higher flow must be served, use EAM.7 to find additional supply or an authorized way of reducing coincident demand. Compare the revised options on that basis. If the existing service obligation and risk criterion are still met, the decision maker may keep the programme. A change to what users are promised requires the responsible authority. EAM.13 brings a material change in demand, risk or obligation back to the choices it affects.