EAM.6:5.1 - A sufficient outage and buffer bound
CityWater’s North area has 1,000 m³/h usable capability before C is modified and needs 700 during the dry work window. Removing A’s 200 leaves 800; removing C’s 300 leaves 700. Each isolated outage passes the quantity bound. Removing both leaves 500, a 200 m³/h shortfall. Their individual feasibility therefore does not justify simultaneous work.
In an additional constructed variant, an independently qualified usable buffer contains 400 m³ and can cover that deficit at the required delivery conditions. The arithmetic gives 400 ÷ 200 = two hours. It cannot support a three-hour combined outage without another qualified contribution. The two-hour limit uses the qualified volume and delivery rate. Tank size alone cannot establish either, and water quality requires its own evidence.
After the selected 200 m³/h addition, normal North capability is 1,200 against the wet minimum of 1,100. To assess a loss of station, power or control, use a scenario or model that includes that loss.