C.11.MV:5.1 - EC-417 Early Stop
The full EC-417 application supplies the receiving problem, alternatives, calculations and the distinct limits used below.
In the constructed EC-417 case, the team must release a controller firmware and harness change on D0. Its software-integration slot is D-21, but signed supplier pinout evidence is expected at D-8. The present question is which proposed way to coordinate that release is worth pursuing under the current constraints.
C.32.MWA.PP §5.3 supplies the timing and capacity comparison:
| Alternative | Proposed way of working | Consequence for this decision |
|---|---|---|
| A | Wait for signed supplier evidence before integrating the software; hold one final board. | With evidence arriving at D-8, the team misses the D-21 slot. Arrival by D-21 removes that timing disadvantage. |
| B | Integrate at D-21 from a versioned provisional edition and reconcile it with signed evidence at D-8. Keep the provisional edition, its uncertainty and its earlier use traceable. The safety engineer performs all 2.00 h of preparation of the changes between editions. | Estimated peak safety demand is 4.40 h, above the 3.20 h limit in an eight-hour day. |
| B2 | Use B’s integration and reconciliation order and retain the same evidence history, but allocate 1.60 h of that preparation to the supplier-configuration role and 0.40 h to the safety engineer. | Estimated peak safety demand is 2.80 h, within the same limit; the supplier’s preparation remains part of the total burden. |
| Stop or next slot | Stop the proposed change or defer the release to an authorized later slot when the required conditions cannot be met. | State the delay or foregone result and the condition needed to reconsider. |
B2 moves preparation work to another role. Verify that its holder can absorb the 1.60 hours in the required window, is qualified to prepare the difference, and can access the relevant evidence under the supplier’s confidentiality conditions. Include the work that allocation displaces and how project, user and provider Systems exchange, check and recover the records through the repository, PLM and CI systems. Three A.15.8.MS support tasks establish only the results observed on those tasks. A three-release WorkPlan describes intended work.
Keep C-EC-Release-v2 as a candidate. Preserve the missing A.22 selection basis, untested AI-provider and feedback branches, and unsupported CUR-EC417-CadenceEffect-1.
With evidence at D−8, A misses the original slot. B exceeds the safety engineer’s limit. B2 reduces the estimated demand on that engineer from 4.40 to 2.80 hours, within 3.20 hours. Recommend at most three trials if B2 also meets the supplier and trial-entry conditions. The responsible holder can select a trial on those grounds. If it cannot proceed, defer or stop, or seek a decision to change the slot for A. Arrival of signed evidence by D−21 would reopen A for the original slot.
An actual release or trial entry still needs every applicable capability, assignment, permission and authority condition. If the question is demonstrated release worth, return the missing performed-release and alternative evidence. The observed support-task results, with the tailoring operation still undefined and its permission/authority stop untested, do not establish that stronger result.