A.3.1:5.2 - Optimization model

Situation and reusable way. JS_Schedule_v4 applies when the jobs, eligible machines, durations, precedence constraints, feasibility rules, and optimization objective are all stated for the scheduling problem. A planner or solver system enacting it constructs candidate assignments under the declared search and stopping rules, rejects infeasible candidates, and compares the remainder by the declared objective. It records the selected schedule, no feasible schedule when infeasibility is established, or no feasible schedule found within the stated search bounds. Missing precedence data, an unstated objective, or incompatible machine eligibility is a stop rather than permission to guess a method variant.

This identification lets a planner compare two solver packages as descriptions of the same scheduling method. The MILP formulation and solver configuration are U.MethodDescription or formal-substrate candidates according to the claim. A feasible schedule can answer a question about what the machines could produce. It qualifies as a U.WorkPlan under A.15.2 when it specifies enough of the intended Work to coordinate it, such as the jobs a work centre is to run in each time window. Adoption of the plan may still be open. The dated solver run is Work, and its decision record is a separate result episteme. To establish production, use evidence of what was actually produced for the relevant jobs and period.