A.15.2:2 - Problem

  1. “Workflow = schedule” conflation. A way-of-doing description is used to answer a scheduling question while time, performer or resource constraints remain unstated.
  2. Plan and occurrence blur. Gantt bars or Kanban tickets are reported as if the work already happened; audits and costing degrade.
  3. Specification and time leakage. A reusable MethodDescription embeds one staffing or calendar choice without distinguishing it from the Method’s required conditions.
  4. Missing comparison basis. Without the planned baseline and applicable comparison rule, a later time, cost or quality difference cannot be classified as plan variance.
  5. Structure entanglement. Equipment or organization structure is copied into a plan without stating which structural relation constrains the intended Work.